Below are the major steps in completing the Civic Place development. Milestones are listed in order of completion dates.
|
July 2007
|
Library temporarily relocated to Level 1 Mandarin Centre, corner Victor Street and Albert Avenue, Chatswood. Full services and facilities continue to be offered. |
|
|
|
September 2007
|
Architectural Design complete |
|
|
|
October - November 2007
|
Call for tenders for construction and call for tenders for demolition |
|
|
|
December 2007
|
The WurliTzer Organ decommissioned and placed in storage for preservation |
|
|
|
January - July 2008
|
Buildings demolished |
|
|
|
August 2008 - February 2009
|
Excavation works |
|
|
|
March 2009 - November 2009
|
Construction of rehearsal room shell |
|
|
|
July 2009 - November 2009
|
Construction of Civic Square / podium |
|
|
|
January 2009 - January 2010
|
Construction of basement 1 carpark |
|
|
|
February 2009 - February 2010
|
Construction of detention tank shell |
|
|
|
November 2009 - March 2010
|
Pouring of top of building concrete |
|
|
|
March 2009 - May 2010
|
Construction of library shell |
|
|
|
August 2009 - June 2010
|
Construction of Civic Hall shell |
|
|
|
August 2009 - July 2010
|
Construction of concert hall shell |
|
|
|
February 2010 - October 2010
|
Construction of facade |
|
|
|
July 2009 - November 2010
|
Construction of theatre shell |
|
|
|
April 2010 - February 2011
|
Concert hall fit-out |
|
|
|
December 2009 - March 2011
|
Library fit-out |
|
|
|
January 2011 - April 2011
|
Concert hall seat installation |
|
|
|
March 2011 - May 2011
|
Theatre seat installation |
|
|
|
July 2010 - May 2011
|
Theatre fit-out |